CSF-J-2026-0125 · Handrail
Handrails — public stair (council)
This job, end to end
QuoteCSF-Q-2026-0134→
JobCSF-J-2026-0125
→Materials3 lines allocated→Fab floorComplete→InvoiceINV-26074
Fabrication progress
Complete- Scheduled
- Detailing
- Materials
- Cutting
- Fabrication
- Finishing
- Install
- Complete
100%
Steel & materials allocated
from the parts this job was quoted on| Code | Description | From part | Qty |
|---|---|---|---|
| CHS-48.3x2.9 | Handrail tube | Wall-mounted handrail (DDA) | 0.166.5m len |
| BRKT-HR | Wall brackets | Wall-mounted handrail (DDA) | 1.2each |
| POWDER-SVC | Powder coat | Wall-mounted handrail (DDA) | 0.4per m² |
Job economics
21%
$3,200 margin on $15,600
Materials (steel, fittings)$4,100
Labour (shop + fit)$4,600
Finish (galv / powder / paint)$1,800
Install & delivery$1,900
Total cost to build$12,400
Contract (ex-GST)$15,600
+ GST 10%$1,560
Total (inc GST)$17,160
Finish: Hot-dip galv · 54 labour hours booked
Crew & dates
- Job owner
- Dean Kovac
- Lead hand
- Sam Whitehill
- Started
- 22 Apr 2026
- Due
- 30 May 2026
Invoice
INV-26074 Overdue
$17,160 inc GST · due 30 June 2026
Pushed to Xero on issue.