→Materials3 lines allocated→Fab floorDetailing→Invoiceon completion
Fabrication progress
Detailing- Scheduled
- Detailing
- Materials
- Cutting
- Fabrication
- Finishing
- Install
- Complete
8%
Steel & materials allocated
from the parts this job was quoted on| Code | Description | From part | Qty |
|---|---|---|---|
| RHS-65x35x2.0 | Top & bottom rail | Powdercoated balustrade panel | 0.288m len |
| FLAT-50x6 | Fixing tabs | Powdercoated balustrade panel | 0.056m len |
| POWDER-SVC | Powder coat | Powdercoated balustrade panel | 2.2per m² |
Job economics
22%
$5,400 margin on $24,600
Materials (steel, fittings)$9,200
Labour (shop + fit)$5,100
Finish (galv / powder / paint)$2,300
Install & delivery$2,600
Total cost to build$19,200
Contract (ex-GST)$24,600
+ GST 10%$2,460
Total (inc GST)$27,060
Finish: 316 SS + glass · 56 labour hours booked
Crew & dates
- Job owner
- Dean Kovac
- Lead hand
- Sam Whitehill
- Started
- 14 July 2026
- Due
- 11 Aug 2026