CSF-J-2026-0129 · Shopfront

Shopfront frame + awning (RSL bistro)

This job, end to end

QuoteCSF-Q-2026-0147
JobCSF-J-2026-0129
Materials0 lines allocatedFab floorFabrication
Invoiceon completion

Fabrication progress

Fabrication
  1. Scheduled
  2. Detailing
  3. Materials
  4. Cutting
  5. Fabrication
  6. Finishing
  7. Install
  8. Complete
48%

Steel & materials allocated

from the parts this job was quoted on
CodeDescriptionFrom partQty
Priced as a custom build — no library parts.

Job economics

19%

$3,100 margin on $16,400

Materials (steel, fittings)$5,400
Labour (shop + fit)$4,600
Finish (galv / powder / paint)$1,900
Install & delivery$1,400
Total cost to build$13,300
Contract (ex-GST)$16,400
+ GST 10%$1,640
Total (inc GST)$18,040

Finish: 2-pack — Bronze · 52 labour hours booked

Customer

Windsor RSL Club

Greg Halloran · Windsor NSW

02 4577 2222 · Terms NET 30

Crew & dates

Job owner
Jarrod Thomas
Lead hand
Cody Barnett
Started
27 June 2026
Due
28 July 2026