CSF-J-2026-0129 · Shopfront
Shopfront frame + awning (RSL bistro)
This job, end to end
QuoteCSF-Q-2026-0147→
JobCSF-J-2026-0129
→Materials0 lines allocated→Fab floorFabrication→Invoiceon completion
Fabrication progress
Fabrication- Scheduled
- Detailing
- Materials
- Cutting
- Fabrication
- Finishing
- Install
- Complete
48%
Steel & materials allocated
from the parts this job was quoted on| Code | Description | From part | Qty |
|---|---|---|---|
| Priced as a custom build — no library parts. | |||
Job economics
19%
$3,100 margin on $16,400
Materials (steel, fittings)$5,400
Labour (shop + fit)$4,600
Finish (galv / powder / paint)$1,900
Install & delivery$1,400
Total cost to build$13,300
Contract (ex-GST)$16,400
+ GST 10%$1,640
Total (inc GST)$18,040
Finish: 2-pack — Bronze · 52 labour hours booked
Crew & dates
- Job owner
- Jarrod Thomas
- Lead hand
- Cody Barnett
- Started
- 27 June 2026
- Due
- 28 July 2026