CSF-J-2026-0130 · Shelter
Bike shelter + rails (school COLA)
This job, end to end
QuoteCSF-Q-2026-0186→
JobCSF-J-2026-0130
→Materials4 lines allocated→Fab floorScheduled→Invoiceon completion
Fabrication progress
Scheduled- Scheduled
- Detailing
- Materials
- Cutting
- Fabrication
- Finishing
- Install
- Complete
0%
Steel & materials allocated
from the parts this job was quoted on| Code | Description | From part | Qty |
|---|---|---|---|
| SHS-89x89x3.5 | Posts | Gable park/playground shelter frame | 1.58m len |
| RHS-100x50x4.0 | Rafters & beams | Gable park/playground shelter frame | 2.28m len |
| PLT-10 | Base plates | Gable park/playground shelter frame | 0.5m² |
| GALV-SVC | Galvanising | Gable park/playground shelter frame | 0.42per tonne |
Job economics
23%
$4,600 margin on $19,800
Materials (steel, fittings)$6,100
Labour (shop + fit)$5,000
Finish (galv / powder / paint)$2,400
Install & delivery$1,700
Total cost to build$15,200
Contract (ex-GST)$19,800
+ GST 10%$1,980
Total (inc GST)$21,780
Finish: Hot-dip galv · 58 labour hours booked
Crew & dates
- Job owner
- Jarrod Thomas
- Lead hand
- Trent Alofi
- Started
- 21 July 2026
- Due
- 18 Aug 2026