CSF-J-2026-0131 · Balustrade

Wire balustrade — deck (Delaney)

This job, end to end

QuoteCSF-Q-2026-0149
JobCSF-J-2026-0131
Materials3 lines allocatedFab floorInstall
Invoiceon completion

Fabrication progress

Install
  1. Scheduled
  2. Detailing
  3. Materials
  4. Cutting
  5. Fabrication
  6. Finishing
  7. Install
  8. Complete
92%

Steel & materials allocated

from the parts this job was quoted on
CodeDescriptionFrom partQty
RHS-65x35x2.0Top & bottom railPowdercoated balustrade panel0.288m len
FLAT-50x6Fixing tabsPowdercoated balustrade panel0.056m len
POWDER-SVCPowder coatPowdercoated balustrade panel2.2per m²

Job economics

15%

$1,200 margin on $7,900

Materials (steel, fittings)$2,650
Labour (shop + fit)$2,200
Finish (galv / powder / paint)$950
Install & delivery$900
Total cost to build$6,700
Contract (ex-GST)$7,900
+ GST 10%$790
Total (inc GST)$8,690

Finish: Powder coat — Surfmist · 26 labour hours booked

Customer

Anthea Delaney

Anthea Delaney · North Richmond NSW

0433 906 210 · Terms 50% deposit / COD

Crew & dates

Job owner
Dean Kovac
Lead hand
Sam Whitehill
Started
20 June 2026
Due
18 July 2026