CSF-J-2026-0134 · Structural
Mezzanine — parts store (McMahon)
This job, end to end
QuoteCSF-Q-2026-0157→
JobCSF-J-2026-0134
→Materials4 lines allocated→Fab floorMaterials→Invoiceon completion
Fabrication progress
Materials- Scheduled
- Detailing
- Materials
- Cutting
- Fabrication
- Finishing
- Install
- Complete
20%
Steel & materials allocated
from the parts this job was quoted on| Code | Description | From part | Qty |
|---|---|---|---|
| SHS-89x89x3.5 | Columns | Mezzanine bay module | 1.28m len |
| RHS-100x50x4.0 | Bearers & joists | Mezzanine bay module | 48m len |
| PLT-10 | Base & cap plates | Mezzanine bay module | 0.8m² |
| PRIME-ZRP | Shop primer | Mezzanine bay module | 0.8tin |
Job economics
21%
$13,300 margin on $63,800
Materials (steel, fittings)$24,500
Labour (shop + fit)$16,200
Finish (galv / powder / paint)$4,200
Install & delivery$5,600
Total cost to build$50,500
Contract (ex-GST)$63,800
+ GST 10%$6,380
Total (inc GST)$70,180
Finish: Shop primer · 190 labour hours booked
Crew & dates
- Job owner
- Jarrod Thomas
- Lead hand
- Sam Whitehill
- Started
- 09 July 2026
- Due
- 28 Aug 2026