CSF-J-2026-0134 · Structural

Mezzanine — parts store (McMahon)

This job, end to end

QuoteCSF-Q-2026-0157
JobCSF-J-2026-0134
Materials4 lines allocatedFab floorMaterials
Invoiceon completion

Fabrication progress

Materials
  1. Scheduled
  2. Detailing
  3. Materials
  4. Cutting
  5. Fabrication
  6. Finishing
  7. Install
  8. Complete
20%

Steel & materials allocated

from the parts this job was quoted on
CodeDescriptionFrom partQty
SHS-89x89x3.5ColumnsMezzanine bay module1.28m len
RHS-100x50x4.0Bearers & joistsMezzanine bay module48m len
PLT-10Base & cap platesMezzanine bay module0.8m²
PRIME-ZRPShop primerMezzanine bay module0.8tin

Job economics

21%

$13,300 margin on $63,800

Materials (steel, fittings)$24,500
Labour (shop + fit)$16,200
Finish (galv / powder / paint)$4,200
Install & delivery$5,600
Total cost to build$50,500
Contract (ex-GST)$63,800
+ GST 10%$6,380
Total (inc GST)$70,180

Finish: Shop primer · 190 labour hours booked

Customer

McMahon Rural Sheds

Paul McMahon · Wilberforce NSW

0418 774 203 · Terms NET 14

Crew & dates

Job owner
Jarrod Thomas
Lead hand
Sam Whitehill
Started
09 July 2026
Due
28 Aug 2026