CSF-J-2026-0136 · Staircase
Feature staircase — architectural (Penrith)
This job, end to end
QuoteCSF-Q-2026-0160→
JobCSF-J-2026-0136
→Materials3 lines allocated→Fab floorOn Hold→Invoiceon completion
Fabrication progress
On Hold- Scheduled
- Detailing
- Materials
- Cutting
- Fabrication
- Finishing
- Install
- Complete
40%
Steel & materials allocated
from the parts this job was quoted on| Code | Description | From part | Qty |
|---|---|---|---|
| PLT-8 | Stringer plate | Straight staircase (steel stringer) | 0.35m² |
| CHQ-5 | Tread | Straight staircase (steel stringer) | 0.32m² |
| GALV-SVC | Galvanising | Straight staircase (steel stringer) | 0.06per tonne |
Job economics
20%
$9,500 margin on $46,500
Materials (steel, fittings)$13,200
Labour (shop + fit)$14,800
Finish (galv / powder / paint)$5,400
Install & delivery$3,600
Total cost to build$37,000
Contract (ex-GST)$46,500
+ GST 10%$4,650
Total (inc GST)$51,150
Finish: 2-pack — client colour · 168 labour hours booked
Crew & dates
- Job owner
- Jarrod Thomas
- Lead hand
- Cody Barnett
- Started
- 26 May 2026
- Due
- 14 Aug 2026