CSF-J-2026-0138 · Staircase

Steel staircase + landing (warehouse)

This job, end to end

QuoteCSF-Q-2026-0168
JobCSF-J-2026-0138
Materials3 lines allocatedFab floorCutting
Invoiceon completion

Fabrication progress

Cutting
  1. Scheduled
  2. Detailing
  3. Materials
  4. Cutting
  5. Fabrication
  6. Finishing
  7. Install
  8. Complete
34%

Steel & materials allocated

from the parts this job was quoted on
CodeDescriptionFrom partQty
PLT-8Stringer plateStraight staircase (steel stringer)0.35m²
CHQ-5TreadStraight staircase (steel stringer)0.32m²
GALV-SVCGalvanisingStraight staircase (steel stringer)0.06per tonne

Job economics

22%

$6,100 margin on $27,800

Materials (steel, fittings)$8,600
Labour (shop + fit)$7,400
Finish (galv / powder / paint)$3,100
Install & delivery$2,600
Total cost to build$21,700
Contract (ex-GST)$27,800
+ GST 10%$2,780
Total (inc GST)$30,580

Finish: Hot-dip galv · 82 labour hours booked

Customer

Grange Constructions

Michael Grange · Rouse Hill NSW

02 8814 7700 · Terms NET 30

Crew & dates

Job owner
Jarrod Thomas
Lead hand
Trent Alofi
Started
06 July 2026
Due
01 Aug 2026