CSF-J-2026-0140 · Handrail
DDA handrails — stair core (Bligh Park)
This job, end to end
QuoteCSF-Q-2026-0170→
JobCSF-J-2026-0140
→Materials3 lines allocated→Fab floorInstall→Invoiceon completion
Fabrication progress
Install- Scheduled
- Detailing
- Materials
- Cutting
- Fabrication
- Finishing
- Install
- Complete
90%
Steel & materials allocated
from the parts this job was quoted on| Code | Description | From part | Qty |
|---|---|---|---|
| CHS-48.3x2.9 | Handrail tube | Wall-mounted handrail (DDA) | 0.166.5m len |
| BRKT-HR | Wall brackets | Wall-mounted handrail (DDA) | 1.2each |
| POWDER-SVC | Powder coat | Wall-mounted handrail (DDA) | 0.4per m² |
Job economics
26%
$2,450 margin on $9,450
Materials (steel, fittings)$2,100
Labour (shop + fit)$2,650
Finish (galv / powder / paint)$900
Install & delivery$1,350
Total cost to build$7,000
Contract (ex-GST)$9,450
+ GST 10%$945
Total (inc GST)$10,395
Finish: Powder coat — Satin Black · 30 labour hours booked
Crew & dates
- Job owner
- Dean Kovac
- Lead hand
- Sam Whitehill
- Started
- 15 June 2026
- Due
- 19 July 2026